Wash. Supreme Court upholds Hanford verdict



By SHANNON DININNY, AP
04 September 2008 @ 04:15 pm ET

YAKIMA, Wash. - The Washington state Supreme Court on Thursday upheld a $4.8 million verdict in favor of 11 pipefitters who claimed they were fired for raising safety concerns at the Hanford nuclear reservation.

Related Topic

Get stories by e-mail on this topic.

E-mail:
Quotes
FLR 44.47 0.05

The workers filed suit nine years ago against Fluor Federal Services, of Richland, a contractor at the south-central Washington nuclear site. They claimed they were laid off after objecting when they were told to install a valve they believed was inadequate.

A Benton County Superior Court jury awarded them damages in 2005. Fluor Federal Services, part of Irving, Texas-based Fluor Corp., appealed, in part arguing that the damage awards were excessive.

The court rejected that argument Thursday, saying, "The awards in question were supported by the evidence."

The Hanford site was created as part of the top-secret Manhattan Project to build an atomic bomb. Today, it is the nation's most contaminated nuclear site.

The event in question occurred at Hanford's tank farms, where underground tanks hold some 53 million gallons of radioactive and hazardous waste left from Cold War-era nuclear weapons production. Some of the 177 aging tanks are known to have leaked, threatening groundwater and the Columbia River less than 10 miles away and making cleanup a priority.

In 1997, a crew of seven pipefitters objected when they were told to install a valve rated for 1,975 pounds per square inch for a test of radioactive waste pipes that would need to withstand 2,235 pounds per square inch.

The crew was later laid off, but a settlement was reached that required Fluor Federal Services to rehire them.

The plaintiffs contend that foremen on the job were told they would have to lay off seven other pipefitters to bring the first seven back. The lawsuit was filed by five of the original seven, plus six of those who were subsequently laid off.

Fluor Federal Services argued that there simply was not enough work at the Hanford site for all the pipefitters.

Copyright 2009 The Associated Press. All rights reserved.
This material may not be published, broadcast, rewritten or redistributed.

    Click!
  • Rate this article:

Comments

Post Your Comment

*Name


advertisement
More Industries
Johnson & Johnson plans to cut up to 7 percent of its workforce in order to generate cost savings needed to finance increasingly costly drug research and...
Belo Corp announced an offering of between $250-275 million of senior notes due in 2016. The notes were issued under a shelf registration filed with the ...
As the world economy begins its journey back, there are emerging market opportunities that were present before the collapse and still remain. The consume...

advertisement
Advertisement
POS Magnetic Card Readers

Online distributor for point of sale equipment, TYSSO and Pegasus.

 
IBTimes.com Web
Partners
International Business Times© 2009 The Ibtimes Company. All Rights Reserved. Terms of service | Privacy Policy | Advertising | About Us | Contact Us | Archives