Trump Halts Army’s Plan To Detonate 10,000 Pounds Of Explosives. Warns Iowa Governor-Elect Of ‘Death Or Destruction.’
A deteriorating military stockpile has triggered a legal and environmental standoff in Iowa. Trump is demanding court and gubernatorial approval before the Army can proceed.

President Donald Trump ordered the U.S. Army on Monday to halt plans to detonate nearly 10,000 pounds of deteriorating explosive material at an Iowa ammunition plant, warning that the state's incoming Democratic governor could be held responsible for any deaths or destruction if the hazardous stockpile is not removed.
The intervention has thrown the Army's latest disposal schedule into uncertainty as military officials warn that 68 barrels of unstable lead azide stored at the Iowa Army Ammunition Plant in Middletown could explode without warning as temperatures fall.
Trump said the controlled detonation would not proceed without approval from the U.S. Court of Appeals for the Eighth Circuit and agreement from Democratic Governor-elect Rob Sand.
"I feel the proper course is to get rid of this longterm problem but, at the same time, have ordered the Military not to do so until such time as the Eighth Circuit agrees that we can go forward," Trump wrote on Truth Social.
The president also made the operation conditional on Sand's agreement, warning that he would hold the incoming governor responsible for "any and all death or destruction" if the hazardous material remained in place and subsequently exploded.
The decision followed days of legal challenges, public opposition and changes to the military's timetable as residents and environmental groups raised concerns about the potential release of toxic lead particles.
The Army had most recently scheduled the controlled detonation for Wednesday, citing favorable weather conditions and additional safety preparations. However, Trump's intervention has left that timetable uncertain.
The operation was originally scheduled for Friday before being repeatedly postponed.
Environmental organizations challenged an emergency permit issued by the Environmental Protection Agency, arguing that federal authorities had not adequately considered alternatives to detonating the explosives in place.
The Eighth Circuit temporarily stayed the permit while considering the legal challenge.
But the Justice Department subsequently informed the court that the Army intended to invoke a separate emergency exemption under federal hazardous waste regulations, arguing that the deteriorating explosives posed an immediate threat to public safety.
In a court filing, government lawyers maintained that the emergency exemption would allow the Army to proceed without relying on the disputed EPA permit.
They argued that the exemption was not affected by the court's administrative stay and that delaying the operation could expose residents to a more dangerous uncontrolled explosion.
The legal argument had not resulted in a publicly confirmed authorization for the operation before Trump's announcement.
The stockpile contains approximately 9,700 pounds of degraded explosive material, including about 6,900 pounds of lead, according to military records cited by Stars and Stripes.
Lead azide is a highly sensitive explosive compound used in military detonators. Army specialists discovered that the material had deteriorated and formed unstable crystals, raising concerns that friction or temperature changes could trigger an accidental explosion.
Military officials have warned that the barrels are too dangerous to move.
Army Col. Aaron Teller, an explosive ordnance disposal specialist, said in a declaration submitted to the appeals court that temperature fluctuations could increase the risk of an uncontrolled detonation.
"Even a small amount of friction can break the crystal formation, causing an explosive chain reaction," Teller said in the court filing.
The Army argued that detonating the explosives in place would allow military specialists to use protective barriers, favorable weather conditions and dust suppression measures to reduce the risk to surrounding communities.
An uncontrolled explosion, by contrast, could scatter explosive material and toxic lead particles without warning or the opportunity to implement those safeguards, military officials warned.
Environmental organizations and residents have questioned whether the planned detonation could itself create serious public health risks.
The operation could release airborne lead particles that travel beyond the ammunition plant, potentially affecting nearby communities, agricultural land and water supplies in Iowa and neighboring Illinois.
Lead exposure can cause serious health problems, particularly in children, and residents have called for greater transparency about the potential environmental consequences.
The Army, Department of Health and Human Services and EPA defended their preparations in a joint statement, saying federal agencies had been coordinating safety measures since March.
"The entire interagency is working together to ensure that the controlled detonation in Middletown, Iowa is conducted in the safest fashion possible," the agencies said.
Federal officials also said they were preparing monitoring and mitigation measures intended to reduce the spread of lead particles and protect surrounding communities.
The dispute has placed Sand, who was elected governor earlier this month, at the center of a federal military decision before he takes office.
Sand questioned why the hazardous materials had been allowed to deteriorate and why officials were now seeking to destroy them under urgent conditions.
"No good options exist and the situation is more dangerous and unpredictable than it ever should have been," Sand wrote in a social media statement cited by The Associated Press.
He also questioned why an earlier contract to address the explosive material had been canceled and why the government had not resolved the problem before it became an immediate safety concern.
"The safety of Iowans should be the top priority of everyone involved," Sand said.
Outgoing Republican Gov. Kim Reynolds, meanwhile, activated Iowa's State Emergency Operations Center on Friday to coordinate preparations among state agencies.
The governor's office said Iowa health officials were evaluating potential public health impacts, while environmental specialists were coordinating with federal authorities to review air, land and water monitoring plans.
State officials were also identifying possible assistance for farmers and livestock producers who could be affected by the detonation.
Reynolds said protecting communities remained the state's highest priority, even though the operation was being directed by the federal government.
Trump's order has now added another obstacle to a disposal operation that military officials describe as increasingly urgent.
The Army maintains that deteriorating explosives could detonate unexpectedly as temperatures drop, while environmental groups warn that a controlled blast could spread hazardous lead dust.
© Copyright IBTimes 2026. All rights reserved.